2026 (ACP) Pavement Resurfacing
Project Description:
Pavement Resurfacing ACP (Asphalt Concrete Pavement “Hot Mix”) for Township Road 524 (Range Road 15 to Range Road 21) & Range Road 21 (Township Road 524 to Township Road 523).
(Actual limits of construction are to be determined, limits may change without notice, follow page for updates.)
Scope of Work:
Resurfacing of the existing Pavement Surface.
Schedule:
Est. Start date: As early as late August/September 2026
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): Border Paving Ltd., Conor McClocklin, 780-446-9773, conorm@borderpaving.com
Consultant: (Secondary Contact): WSP, Clayton Kolkman, 587-489-0134, clayton.kolkman@wsp.com
Parkland Project Officer: Dan Spray, 780-968-8353, dan.spray@parklandcounty.com
Updates:
August 31, 2026: Construction to start September 1, 2026, weather dependent. Please see the construction notice attached.
August 2026: Construction contract was awarded to Border Paving Ltd. Construction on Township Road 524 and Range Road 21 anticipated to start in August/September. Willow Peak Estates Subdivision Road was deleted from the program due to insufficient funding in 2026.
June 2026: RFQ posted. Construction anticipated to start in July/August.
May 2026: Engineering design being finalized with RFQ anticipated to be posted in June.
March 2026: Engineering consultant has been engaged to complete the asphalt surfacing engineering design; construction is anticipated to start as early as July 2026.