2026 (ACP) Pavement Resurfacing

Share 2026 (ACP) Pavement Resurfacing on Facebook Share 2026 (ACP) Pavement Resurfacing on X (formerly Twitter) Share 2026 (ACP) Pavement Resurfacing on Linkedin Email 2026 (ACP) Pavement Resurfacing link

Project Description:

Pavement Resurfacing ACP (Asphalt Concrete Pavement “Hot Mix”) for Township Road 524 (Range Road 15 to Range Road 21) & Range Road 21 (Township Road 524 to Township Road 523).

(Actual limits of construction are to be determined, limits may change without notice, follow page for updates.)


Scope of Work:

Resurfacing of the existing Pavement Surface.


Schedule:

Est. Start date: As early as late August/September 2026

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Contractor (Primary Contact): Border Paving Ltd., Conor McClocklin, 780-446-9773, conorm@borderpaving.com

Consultant: (Secondary Contact): WSP, Clayton Kolkman, 587-489-0134, clayton.kolkman@wsp.com

Parkland Project Officer: Dan Spray, 780-968-8353, dan.spray@parklandcounty.com


Updates:

August 31, 2026: Construction to start September 1, 2026, weather dependent. Please see the construction notice attached.

August 2026: Construction contract was awarded to Border Paving Ltd. Construction on Township Road 524 and Range Road 21 anticipated to start in August/September. Willow Peak Estates Subdivision Road was deleted from the program due to insufficient funding in 2026.

June 2026: RFQ posted. Construction anticipated to start in July/August.

May 2026: Engineering design being finalized with RFQ anticipated to be posted in June.

March 2026: Engineering consultant has been engaged to complete the asphalt surfacing engineering design; construction is anticipated to start as early as July 2026.


Location:




Project Description:

Pavement Resurfacing ACP (Asphalt Concrete Pavement “Hot Mix”) for Township Road 524 (Range Road 15 to Range Road 21) & Range Road 21 (Township Road 524 to Township Road 523).

(Actual limits of construction are to be determined, limits may change without notice, follow page for updates.)


Scope of Work:

Resurfacing of the existing Pavement Surface.


Schedule:

Est. Start date: As early as late August/September 2026

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Contractor (Primary Contact): Border Paving Ltd., Conor McClocklin, 780-446-9773, conorm@borderpaving.com

Consultant: (Secondary Contact): WSP, Clayton Kolkman, 587-489-0134, clayton.kolkman@wsp.com

Parkland Project Officer: Dan Spray, 780-968-8353, dan.spray@parklandcounty.com


Updates:

August 31, 2026: Construction to start September 1, 2026, weather dependent. Please see the construction notice attached.

August 2026: Construction contract was awarded to Border Paving Ltd. Construction on Township Road 524 and Range Road 21 anticipated to start in August/September. Willow Peak Estates Subdivision Road was deleted from the program due to insufficient funding in 2026.

June 2026: RFQ posted. Construction anticipated to start in July/August.

May 2026: Engineering design being finalized with RFQ anticipated to be posted in June.

March 2026: Engineering consultant has been engaged to complete the asphalt surfacing engineering design; construction is anticipated to start as early as July 2026.


Location:




Page last updated: 31 Aug 2026, 04:04 PM