2026 Surfaced Road Reconstruction Program (SRRP)
Project Description:
Road reconstruction to strengthen the existing base of the road, field and residential approaches. A new ASBC surface will be placed, all work to take place on Twp. 534 from RR 272 to 500m west of RR 271- Including the intersection at Twp. 534 and RR 272.
Scope of Work:
This project includes reshaping and compacting the existing road materials, followed by placement of a new cold mix (ASBC) surface.
Schedule:
Est. Start date: Summer, 2026 – Fall 2026
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): TBD
Consultant: (Secondary Contact): CIMA+, Parsa Shirvanito
Parkland Project Officer: Trevor Lucas, 780-800-9311, trevor.lucas@parklandcounty.com
Updates:
August 24, 2026: RFQ has been awarded to Central Civil Solutions, construction is expected to start early September and be completed by October 15, 2026
June 4, 2026: Preliminary design is in progress with construction anticipated for August 2026.
May 4, 2026: Engineering consultant services have been awarded, construction is anticipated for August 2026.
February 25, 2026: RFP to be awarded for consulting services – RFQ to be awarded for construction services
Location:
Twp. 534, RR 272 to 500m west RR 271 – Including intersection at Twp. 534 and RR 272.