255 St (Twp Rd 530A) Water Line Extension

Share 255 St (Twp Rd 530A) Water Line Extension on Facebook Share 255 St (Twp Rd 530A) Water Line Extension on Twitter Share 255 St (Twp Rd 530A) Water Line Extension on Linkedin Email 255 St (Twp Rd 530A) Water Line Extension link

Project Description:

Construction of Water Line Extension along 255 St (Township Rd 530A)


**255 St is closed under a staged road closure until November 8, 2025. See Road closure phase and detour plan below**


Scope of Work:

Installation of approximately 1,000 m of water line via Horizontal Directional Drilling under Hwy 16A and open cut installation along 255 St.


Schedule:

Est. Start date: August 25, 2025

Est. Completion Date: November 15, 2025

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Contractor (Primary Contact): CKB Construction, Project Manager – Jason Stiksma,

780-453-6611, jstiksma@ckbconstruction.com

Consultant (Secondary Contact): CIMA+, Site Inspector – Ethan Li, 780-297-2462, ethan.li@cima.ca

Parkland Project Manager: Franco Giammarioli, 780-968-8888 ext.8390,

franco.giammarioli@parklandcounty.com


Updates:

October 10, 2025: The 255 St project has now shifted to the Phase 2 road closure (see photos). Open trench water line and hydrant installations are ongoing along 255 St.

September 26, 2025: 255 St is closed under the Phase 1 road closure (see below). Horizontal directional drilling of the waterline across Hwy 16A is complete and open trench water line installations are ongoing along 255 St.

August 25, 2025: CKB Construction is set to begin mobilization for the 255 St Water Line Extension project. Single lane alternative traffic accommodations will be in place on 255 St.

Staged Detour:

Phase 2 road closure


Location:


Project Description:

Construction of Water Line Extension along 255 St (Township Rd 530A)


**255 St is closed under a staged road closure until November 8, 2025. See Road closure phase and detour plan below**


Scope of Work:

Installation of approximately 1,000 m of water line via Horizontal Directional Drilling under Hwy 16A and open cut installation along 255 St.


Schedule:

Est. Start date: August 25, 2025

Est. Completion Date: November 15, 2025

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Contractor (Primary Contact): CKB Construction, Project Manager – Jason Stiksma,

780-453-6611, jstiksma@ckbconstruction.com

Consultant (Secondary Contact): CIMA+, Site Inspector – Ethan Li, 780-297-2462, ethan.li@cima.ca

Parkland Project Manager: Franco Giammarioli, 780-968-8888 ext.8390,

franco.giammarioli@parklandcounty.com


Updates:

October 10, 2025: The 255 St project has now shifted to the Phase 2 road closure (see photos). Open trench water line and hydrant installations are ongoing along 255 St.

September 26, 2025: 255 St is closed under the Phase 1 road closure (see below). Horizontal directional drilling of the waterline across Hwy 16A is complete and open trench water line installations are ongoing along 255 St.

August 25, 2025: CKB Construction is set to begin mobilization for the 255 St Water Line Extension project. Single lane alternative traffic accommodations will be in place on 255 St.

Staged Detour:

Phase 2 road closure


Location:


Page last updated: 24 Oct 2025, 02:31 PM