255 St (Twp Rd 530A) Water Line Extension
Project Description:
Construction of Water Line Extension along 255 St (Township Rd 530A)
**255 St is closed under a staged road closure until November 8, 2025. See Road closure phase and detour plan below**
Scope of Work:
Installation of approximately 1,000 m of water line via Horizontal Directional Drilling under Hwy 16A and open cut installation along 255 St.
Schedule:
Est. Start date: August 25, 2025
Est. Completion Date: November 15, 2025
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): CKB Construction, Project Manager – Jason Stiksma,
780-453-6611, jstiksma@ckbconstruction.com
Consultant (Secondary Contact): CIMA+, Site Inspector – Ethan Li, 780-297-2462, ethan.li@cima.ca
Parkland Project Manager: Franco Giammarioli, 780-968-8888 ext.8390,
franco.giammarioli@parklandcounty.com
Updates:
October 10, 2025: The 255 St project has now shifted to the Phase 2 road closure (see photos). Open trench water line and hydrant installations are ongoing along 255 St.
September 26, 2025: 255 St is closed under the Phase 1 road closure (see below). Horizontal directional drilling of the waterline across Hwy 16A is complete and open trench water line installations are ongoing along 255 St.
August 25, 2025: CKB Construction is set to begin mobilization for the 255 St Water Line Extension project. Single lane alternative traffic accommodations will be in place on 255 St.
Staged Detour:
Phase 2 road closure


Location: