Asphalt Surfacing Projects (ASBC)

Share Asphalt Surfacing Projects (ASBC) on Facebook Share Asphalt Surfacing Projects (ASBC) on Twitter Share Asphalt Surfacing Projects (ASBC) on Linkedin Email Asphalt Surfacing Projects (ASBC) link

Project Description:

ASBC (Asphalt Stabilized Base Course Aka. Cold mix Asphalt) Road surfacing for various locations throughout the County as shown on the following maps.


Scope of Work:

New ASBC pavement will be placed on Grid (Range Roads & Twp. Roads) and Subdivision roads. This work is part of the Asphalt Surfacing Program and the Subdivision Preservation Program as outlined in the Capital Infrastructure Program found here; https://www.parklandcounty.com/en/roads-and-transportation/current-capital-infrastructure-program.aspx.


Schedule:

Est. Start date: May 28, 2024, to September 2024.

See schedule on the next pages for the planned construction sequence.

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Parkland Project Officer: Trevor Lucas, 780-968-8888 Ext 8610, trevor.lucas@parklandcounty.com


Updates:

September 25, 2024: Range Road 21, north of Hwy 16 service road to approximately 160m North of Spruce Valley Estates South entrance, has been completed and was the last project to completed in the 2024 construction season. No further work will be carried out by Engineering Services. The 2025 ASBC program locations and schedule will be presented in the new year.

August 22, 2024: The 2024 ASBC surfacing program will be completed this week. Because there is capacity, material and schedule availability, the County is planning to complete one additional project location that was slated for 2025, yet this year! This site is Range Road 21, north of Hwy 16 service road to approximately 160m North of Spruce Valley Estates South entrance. This additional project site is now scheduled to be completed by August 27th this year. location picture added in the photo section.

July 19, 2024: Completed surfacing on RR 55, Princess Estates, Deer Park I, RR 270, Twp 512 Holborn Rd, and RR 14. Will be starting Neutral Valley on Monday July 22, 2024.

July 18, 2024: 2024 ASBC program is approx. 50% complete. Work is performed in stages, the segment of road will be oiled, the main road will be surfaced with ASBC then the approaches will be completed with intersections. The finished surface of the road will have another layer of oil placed towards the end of the construction season. There will be some delays please be patient and obey signs and flaggers.

June 18, 2024: Contractor has completed work on RR55 & Princess Estates.

May 17, 2024: Roads scheduled to start have notice signs posted in the areas. Crews and equipment are ready to begin, and the roads have already been prepped.


Location:



Project Description:

ASBC (Asphalt Stabilized Base Course Aka. Cold mix Asphalt) Road surfacing for various locations throughout the County as shown on the following maps.


Scope of Work:

New ASBC pavement will be placed on Grid (Range Roads & Twp. Roads) and Subdivision roads. This work is part of the Asphalt Surfacing Program and the Subdivision Preservation Program as outlined in the Capital Infrastructure Program found here; https://www.parklandcounty.com/en/roads-and-transportation/current-capital-infrastructure-program.aspx.


Schedule:

Est. Start date: May 28, 2024, to September 2024.

See schedule on the next pages for the planned construction sequence.

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Parkland Project Officer: Trevor Lucas, 780-968-8888 Ext 8610, trevor.lucas@parklandcounty.com


Updates:

September 25, 2024: Range Road 21, north of Hwy 16 service road to approximately 160m North of Spruce Valley Estates South entrance, has been completed and was the last project to completed in the 2024 construction season. No further work will be carried out by Engineering Services. The 2025 ASBC program locations and schedule will be presented in the new year.

August 22, 2024: The 2024 ASBC surfacing program will be completed this week. Because there is capacity, material and schedule availability, the County is planning to complete one additional project location that was slated for 2025, yet this year! This site is Range Road 21, north of Hwy 16 service road to approximately 160m North of Spruce Valley Estates South entrance. This additional project site is now scheduled to be completed by August 27th this year. location picture added in the photo section.

July 19, 2024: Completed surfacing on RR 55, Princess Estates, Deer Park I, RR 270, Twp 512 Holborn Rd, and RR 14. Will be starting Neutral Valley on Monday July 22, 2024.

July 18, 2024: 2024 ASBC program is approx. 50% complete. Work is performed in stages, the segment of road will be oiled, the main road will be surfaced with ASBC then the approaches will be completed with intersections. The finished surface of the road will have another layer of oil placed towards the end of the construction season. There will be some delays please be patient and obey signs and flaggers.

June 18, 2024: Contractor has completed work on RR55 & Princess Estates.

May 17, 2024: Roads scheduled to start have notice signs posted in the areas. Crews and equipment are ready to begin, and the roads have already been prepped.


Location:



Page last updated: 25 Sep 2024, 02:28 PM