Project Description:
Replacement of Bridge File 13218 on RR 73 South of Twp 514
Scope of Work:
Removal of the existing bridge culvert and installation of a new bridge culvert. The road will be closed, and traffic will be detoured to an alternate route for the duration of construction.
Upgrading of Range Road 73 is not included in the project scope.
Schedule:
Est. TBD late 2026 or summer of 2027 (subject to award and approvals). Construction is anticipated to require approximately 4 weeks of active work.
Schedule can change without notice, follow page for monthly updates.
August 2026: The RFQ has been posted. Contract award is anticipated in September 2026. The estimated construction start date will be determined following award.
Location:
Project Description:
Replacement of Bridge File 13218 on RR 73 South of Twp 514
Scope of Work:
Removal of the existing bridge culvert and installation of a new bridge culvert. The road will be closed, and traffic will be detoured to an alternate route for the duration of construction.
Upgrading of Range Road 73 is not included in the project scope.
Schedule:
Est. TBD late 2026 or summer of 2027 (subject to award and approvals). Construction is anticipated to require approximately 4 weeks of active work.
Schedule can change without notice, follow page for monthly updates.
August 2026: The RFQ has been posted. Contract award is anticipated in September 2026. The estimated construction start date will be determined following award.