Bridge Replacement – RR32, South of TWP Road 530 File 7409
Share Bridge Replacement – RR32, South of TWP Road 530 File 7409 on Facebook
Share Bridge Replacement – RR32, South of TWP Road 530 File 7409 on Twitter
Share Bridge Replacement – RR32, South of TWP Road 530 File 7409 on Linkedin
Email Bridge Replacement – RR32, South of TWP Road 530 File 7409 link
Project Description:
Parkland County is undertaking a design and replacement of BF 7409, located on Range Road 32, south of Twp Road 530.
Scope of Work:
The consultant will:
- Complete the design of BF 7409
- Complete the design of the detour route for residents as construction starts
Upgrading Range Road 32 is not part of the scope.
Schedule:
Est. Start date: March 2026 – TBD
Approximately 4-6 weeks of active construction.
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Consultant: Kirk Morris, 780-267-7723, kirk.morris@mpaeng.ca
Parkland Project Engineer-In-Training: Balbina Nagera, 780-691-4598, balbina.nagera@parklandcounty.com
Updates:
March 2026: Project has been successfully awarded and project has started.
Location:

Page last updated: 24 Mar 2026, 12:55 PM