Project Description:
Replacement of existing sanitary force main and installation of a new watermain crossing within Entwistle, Alberta.
Scope of Work:
Detailed design and construction of water and wastewater infrastructure in Entwistle. The Project includes replacement of the existing sanitary force main and installing a new watermain connecting to the Entwistle Reservoir. Both the sanitary force main and the watermain will involve directional drilling beneath HWY 16 and CN Rail which requires extensive prework and permitting to proceed. Additional scope items include replacement of existing watermain on 45 Avenue, tying into new Reservoir, tying into existing watermain on 48 Avenue, tying new sanitary force main into lift station on 46 Avenue, and replacement of force main outlet manhole on 48 Avenue.
Schedule:
Geotechnical Investigation: October 7 and 8, 2025
Detailed Design: October 2025 – March 2026
Est. Construction Start date: Spring/Summer of 2026
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): Pending Contract Award
October 1, 2025 – Project moving from preliminary design stage into detailed design. Geotechnical investigation tentatively scheduled for October 7 and 8, 2025.
Location:
Entwistle, AB
Project Description:
Replacement of existing sanitary force main and installation of a new watermain crossing within Entwistle, Alberta.
Scope of Work:
Detailed design and construction of water and wastewater infrastructure in Entwistle. The Project includes replacement of the existing sanitary force main and installing a new watermain connecting to the Entwistle Reservoir. Both the sanitary force main and the watermain will involve directional drilling beneath HWY 16 and CN Rail which requires extensive prework and permitting to proceed. Additional scope items include replacement of existing watermain on 45 Avenue, tying into new Reservoir, tying into existing watermain on 48 Avenue, tying new sanitary force main into lift station on 46 Avenue, and replacement of force main outlet manhole on 48 Avenue.
Schedule:
Geotechnical Investigation: October 7 and 8, 2025
Detailed Design: October 2025 – March 2026
Est. Construction Start date: Spring/Summer of 2026
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): Pending Contract Award
October 1, 2025 – Project moving from preliminary design stage into detailed design. Geotechnical investigation tentatively scheduled for October 7 and 8, 2025.