Project Description:
Design of Meridian Avenue from West of Range Road 261A to Countryside Ravines III.
**Notice: No public access October 21st East of Countryside Ravines & West of Country Squire Estates
Scope of Work:
Design and construction of Meridian Avenue including a stormwater analysis to tie the existing Meridian Avenue sections together.
Schedule:
Est. Start date: Preliminary Engineering started August 2025. Construction TBD.
Schedule can change without notice, follow page for monthly updates.
Parkland Project Officer: Dan Spray, 780-968-8353, dan.spray@parklandcounty.com
Updates:
January 2026: Design being finalized. Construction anticipated in 2027. No updates expected until Fall 2026.
October 20, 2025: Hydrovac investigation will be completed on October 21st, 2025.
October 2025: Preliminary Engineering is ongoing.
September 2025: Preliminary Engineering is ongoing.
August 14, 2025: Notice: Geotechnical investigation drilling will be completed between August 19th and August 22nd, 2025. No public access East of Countryside Estates and West of Country Squire Estates.
July 2025: Engineering consultant awarded project. Preliminary Engineering drawings to start Q3 2025.
Location:
Project Description:
Design of Meridian Avenue from West of Range Road 261A to Countryside Ravines III.
**Notice: No public access October 21st East of Countryside Ravines & West of Country Squire Estates
Scope of Work:
Design and construction of Meridian Avenue including a stormwater analysis to tie the existing Meridian Avenue sections together.
Schedule:
Est. Start date: Preliminary Engineering started August 2025. Construction TBD.
Schedule can change without notice, follow page for monthly updates.
Parkland Project Officer: Dan Spray, 780-968-8353, dan.spray@parklandcounty.com
Updates:
January 2026: Design being finalized. Construction anticipated in 2027. No updates expected until Fall 2026.
October 20, 2025: Hydrovac investigation will be completed on October 21st, 2025.
October 2025: Preliminary Engineering is ongoing.
September 2025: Preliminary Engineering is ongoing.
August 14, 2025: Notice: Geotechnical investigation drilling will be completed between August 19th and August 22nd, 2025. No public access East of Countryside Estates and West of Country Squire Estates.
July 2025: Engineering consultant awarded project. Preliminary Engineering drawings to start Q3 2025.