Osprey Sanitary Replacement

Share Osprey Sanitary Replacement on Facebook Share Osprey Sanitary Replacement on Twitter Share Osprey Sanitary Replacement on Linkedin Email Osprey Sanitary Replacement link

**Certain roads and areas on the roads will be barricaded until late spring/early summer until further repairs and action can occur after the weather cycles. Accessibility to resident homes within the subdivision will be maintained during this time. **


Project Description:

As part of an overall wastewater rehabilitation program in Wabamun, a replacement of all sanitary lines and manholes will be completed within the Osprey subdivision.


*Residents might also experience some short terms water shutdowns but will be notified accordingly. They will be set up on temporary water for the duration of construction to avoid any impacts*


Scope of Work:

Work will include replacement of all sanitary main lines and manholes within the Osprey subdivision. Service laterals that are in good condition will be reconnected to the new main lines and service laterals that are in poor condition will be replaced to property line. Lines and manholes will be replaced using open cut trenching, therefore the road and minor locations within the sidewalks will be disturbed during construction and returned to existing upon completion.


Schedule:

Est. Start date: July 2024 – December 2024

Schedule can change without notice, follow page for monthly updates.


Project Co-Ordinator:

Contractor, GS Construction (Primary Contact): Ben Jamer, 780-962-3544, ben.jamer@gsconstruction.ca

Consultant, ISL Engineering (Secondary Contact): Ahmed Al-Musawi, 780-438-9000, AAL-Musawi@islengineering.com

Parkland Project Officer: Sydney Gordon, 780-968-8888 ext. 8452, sydney.gordon@parklandcounty.com


Updates:

December 2024: Weather has impacted the completion of deficiency items and GS will continue to work to finish up any items this month and will return in the spring for seasonal items.

November 2024: GS has completed the scope of work for replacement of the mains and services and is working on completing deficiencies to finalize the project.

October 2024: GS has completed 75% of the sanitary main replacement along 55 St, full replacement of the sanitary main along 52A Ave, and has begun the replacement along 52 Ave. Surface works have begun for sidewalk and road surface patching. This project is on track to be completed in October.

September 2024: Work has been completed from the lift station at the North end of 55 St. to about halfway down 55 St. They will continue working on the main line and manholes for the month of September along 55 St, moving onto 52A Ave, and then finally 52 Ave.

August 2024: GS Construction has begun work on the North side of the project limits and will continue down 55th Street for their first phase. Residents will be set up with temporary water to avoid any impacts and there will be temporary road shutdowns.

July 2024: GS Construction will mobilize to site and begin their preliminary works prior to construction.

June 2024: Completing pre-construction paperwork prior to mobilization for July.

May 2024: No Change.

April 2024: No Change.

March 2024: Completing pre-construction paperwork prior to mobilization for the beginning of June, 2024.



Location:




**Certain roads and areas on the roads will be barricaded until late spring/early summer until further repairs and action can occur after the weather cycles. Accessibility to resident homes within the subdivision will be maintained during this time. **


Project Description:

As part of an overall wastewater rehabilitation program in Wabamun, a replacement of all sanitary lines and manholes will be completed within the Osprey subdivision.


*Residents might also experience some short terms water shutdowns but will be notified accordingly. They will be set up on temporary water for the duration of construction to avoid any impacts*


Scope of Work:

Work will include replacement of all sanitary main lines and manholes within the Osprey subdivision. Service laterals that are in good condition will be reconnected to the new main lines and service laterals that are in poor condition will be replaced to property line. Lines and manholes will be replaced using open cut trenching, therefore the road and minor locations within the sidewalks will be disturbed during construction and returned to existing upon completion.


Schedule:

Est. Start date: July 2024 – December 2024

Schedule can change without notice, follow page for monthly updates.


Project Co-Ordinator:

Contractor, GS Construction (Primary Contact): Ben Jamer, 780-962-3544, ben.jamer@gsconstruction.ca

Consultant, ISL Engineering (Secondary Contact): Ahmed Al-Musawi, 780-438-9000, AAL-Musawi@islengineering.com

Parkland Project Officer: Sydney Gordon, 780-968-8888 ext. 8452, sydney.gordon@parklandcounty.com


Updates:

December 2024: Weather has impacted the completion of deficiency items and GS will continue to work to finish up any items this month and will return in the spring for seasonal items.

November 2024: GS has completed the scope of work for replacement of the mains and services and is working on completing deficiencies to finalize the project.

October 2024: GS has completed 75% of the sanitary main replacement along 55 St, full replacement of the sanitary main along 52A Ave, and has begun the replacement along 52 Ave. Surface works have begun for sidewalk and road surface patching. This project is on track to be completed in October.

September 2024: Work has been completed from the lift station at the North end of 55 St. to about halfway down 55 St. They will continue working on the main line and manholes for the month of September along 55 St, moving onto 52A Ave, and then finally 52 Ave.

August 2024: GS Construction has begun work on the North side of the project limits and will continue down 55th Street for their first phase. Residents will be set up with temporary water to avoid any impacts and there will be temporary road shutdowns.

July 2024: GS Construction will mobilize to site and begin their preliminary works prior to construction.

June 2024: Completing pre-construction paperwork prior to mobilization for July.

May 2024: No Change.

April 2024: No Change.

March 2024: Completing pre-construction paperwork prior to mobilization for the beginning of June, 2024.