Osprey Sanitary Replacement

Share Osprey Sanitary Replacement on Facebook Share Osprey Sanitary Replacement on Twitter Share Osprey Sanitary Replacement on Linkedin Email Osprey Sanitary Replacement link

**Certain roads and areas on the roads will be barricaded until summer of 2026 until further repairs and action can occur after the weather cycles. Accessibility to resident homes within the subdivision will be maintained during this time. **


Project Description:

As part of an overall wastewater rehabilitation program in Wabamun, a replacement of the water lines on 52 and 52A avenues and of all sanitary lines and manholes will be completed within the Osprey subdivision.


Scope of Work:

Water lines on 52A and 52 avenues as well as all sanitary main lines and manholes were replaced within the Osprey subdivision. Service laterals that are in good condition will be reconnected to the new main lines and service laterals that are in poor condition will be replaced to property line. Lines and manholes will be replaced using open cut trenching, therefore the road and minor locations within the sidewalks will be disturbed during construction and returned to existing upon completion.


*Residents might also experience some short term water shutdowns but will be notified accordingly. They will be set up on temporary water for the duration of construction to avoid any impacts. *


Schedule:

Est. Start date: July 2024 – December 2025 (May-July 2026 for seasonal deficiencies)

Schedule can change without notice, follow page for monthly updates.


Project Co-Ordinator:

Contractor, GS Construction (Primary Contact): Michael Putt, 780-962-3544, michael.putt@gsconstruction.ca

Parkland Project Officer: Christine Marleau, 780-968-8888, christine.marleau@parklandcounty.com


Updates:

March 2026: Contractor will be returning in 2026 to complete seasonal deficiencies, which consist of minor road surfacing works.

January 2026: GS has successfully finalized the additional scope of work for the replacement of the watermain along 52 and 52A Avenue. While the primary construction phase is now complete, minor road surfacing works remain pending and are slated for completion in the spring of 2026. Until these final works are finished, 52 and 52A Avenue will remain barricaded and closed to traffic.

August 2025: No Update

July 2025: Please see attached "Notice of Construction"

July 2025: Deficiency work is underway and planned to be completed by mid-August.

May 2025: Deficiency work will begin and planned to be completed by the end of June.

December 2024: Weather has impacted the completion of deficiency items and GS will continue to work to finish up any items this month and will return in the spring for seasonal items.

November 2024: GS has completed the scope of work for replacement of the mains and services and is working on completing deficiencies to finalize the project.

October 2024: GS has completed 75% of the sanitary main replacement along 55 St, full replacement of the sanitary main along 52A Ave, and has begun the replacement along 52 Ave. Surface works have begun for sidewalk and road surface patching. This project is on track to be completed in October.

September 2024: Work has been completed from the lift station at the North end of 55 St. to about halfway down 55 St. They will continue working on the main line and manholes for the month of September along 55 St, moving onto 52A Ave, and then finally 52 Ave.

August 2024: GS Construction has begun work on the North side of the project limits and will continue down 55th Street for their first phase. Residents will be set up with temporary water to avoid any impacts and there will be temporary road shutdowns.

July 2024: GS Construction will mobilize to site and begin their preliminary works prior to construction.

June 2024: Completing pre-construction paperwork prior to mobilization for July.

May 2024: No Change.

April 2024: No Change.

March 2024: Completing pre-construction paperwork prior to mobilization for the beginning of June, 2024.



Location:




**Certain roads and areas on the roads will be barricaded until summer of 2026 until further repairs and action can occur after the weather cycles. Accessibility to resident homes within the subdivision will be maintained during this time. **


Project Description:

As part of an overall wastewater rehabilitation program in Wabamun, a replacement of the water lines on 52 and 52A avenues and of all sanitary lines and manholes will be completed within the Osprey subdivision.


Scope of Work:

Water lines on 52A and 52 avenues as well as all sanitary main lines and manholes were replaced within the Osprey subdivision. Service laterals that are in good condition will be reconnected to the new main lines and service laterals that are in poor condition will be replaced to property line. Lines and manholes will be replaced using open cut trenching, therefore the road and minor locations within the sidewalks will be disturbed during construction and returned to existing upon completion.


*Residents might also experience some short term water shutdowns but will be notified accordingly. They will be set up on temporary water for the duration of construction to avoid any impacts. *


Schedule:

Est. Start date: July 2024 – December 2025 (May-July 2026 for seasonal deficiencies)

Schedule can change without notice, follow page for monthly updates.


Project Co-Ordinator:

Contractor, GS Construction (Primary Contact): Michael Putt, 780-962-3544, michael.putt@gsconstruction.ca

Parkland Project Officer: Christine Marleau, 780-968-8888, christine.marleau@parklandcounty.com


Updates:

March 2026: Contractor will be returning in 2026 to complete seasonal deficiencies, which consist of minor road surfacing works.

January 2026: GS has successfully finalized the additional scope of work for the replacement of the watermain along 52 and 52A Avenue. While the primary construction phase is now complete, minor road surfacing works remain pending and are slated for completion in the spring of 2026. Until these final works are finished, 52 and 52A Avenue will remain barricaded and closed to traffic.

August 2025: No Update

July 2025: Please see attached "Notice of Construction"

July 2025: Deficiency work is underway and planned to be completed by mid-August.

May 2025: Deficiency work will begin and planned to be completed by the end of June.

December 2024: Weather has impacted the completion of deficiency items and GS will continue to work to finish up any items this month and will return in the spring for seasonal items.

November 2024: GS has completed the scope of work for replacement of the mains and services and is working on completing deficiencies to finalize the project.

October 2024: GS has completed 75% of the sanitary main replacement along 55 St, full replacement of the sanitary main along 52A Ave, and has begun the replacement along 52 Ave. Surface works have begun for sidewalk and road surface patching. This project is on track to be completed in October.

September 2024: Work has been completed from the lift station at the North end of 55 St. to about halfway down 55 St. They will continue working on the main line and manholes for the month of September along 55 St, moving onto 52A Ave, and then finally 52 Ave.

August 2024: GS Construction has begun work on the North side of the project limits and will continue down 55th Street for their first phase. Residents will be set up with temporary water to avoid any impacts and there will be temporary road shutdowns.

July 2024: GS Construction will mobilize to site and begin their preliminary works prior to construction.

June 2024: Completing pre-construction paperwork prior to mobilization for July.

May 2024: No Change.

April 2024: No Change.

March 2024: Completing pre-construction paperwork prior to mobilization for the beginning of June, 2024.



Location: