Prospector's Point Road, Twp 511 (Graminia Rd.) to Recreation Area
Project Description:
Prospector's Point Road (RR 263 & Twp. 510A) providing access to the Devonian Trail & Prospector’s Point public use area, will undergo design & rehabilitation work.
Scope of Work:
The project includes preliminary design which is focused on improving road condition and rideability.
Schedule:
Est. Start date: Detailed Design started January 2025.
Construction expected late summer or early fall of 2025.
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Consultant: (Primary Contact): CIMA+, Coulombe, Russ, 780-232-2493, russ.coulombe@cima.ca
Parkland Project Officer: Jeremy Hemsing, 780-968-8888 ext. 8119, jeremy.hemsing@parklandcounty.com
Updates:
April 28, 2025: Detailed design nearing completion. Construction anticipated in late summer August/September 2025.
March 25, 2025: No update.
February 06, 2025: Detailed design is ongoing.
December 11, 2024: Preliminary design is complete. Regulatory approvals are being submitted. Detailed design will commence in January 2025.
September 11, 2024: Design continues to progress. The project update to the Governance and Priorities Committee (GPC) has been rescheduled for December 3, 2024.
August 2, 2024: Design is progressing. A project update to the Governance and Priorities Committee (GPC) is tentatively scheduled for October 1, 2024.
June 10, 2024: Consultant has begun work with Geotechnical site investigations starting July 10
Notice – There will be a one-day road closure to the parking lot for vehicles at the South-West side of the Hwy bridge on July 11. Vehicle parking will be identified on site and pedestrian traffic will be accommodated to the parking lot and the trailhead via the existing trail network.
May 2024: Parkland County is currently procuring a consultant to complete the design.
Location: