Range Road 32 Pavement Rehabilitation
Project Description:
Pavement Rehabilitation of Range Road 32 (Duffield Road) South of Highway 16 to Fairchild Ave.
Scope of Work:
Pavement Rehabilitation of the existing Paved Surface.
Schedule:
Est. Start date: September 2, 2025
Est. Completion date: October 15, 2025.
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): E Construction, Andre Blanchard, 780-983-3244, andre.blanchard@ecltd.ca
Consultant: (Secondary Contact): CIMA+, Parsa Shirvani, 780-297-2462, parsa.shirvani@cima.ca
Parkland Project Officer: Dan Spray, 780-968-8888 Ext 8353, dan.spray@parklandcounty.com
Updates:
November 17, 2025: Project is complete and in warranty period. No further updates expected until 2027.
October 6, 2025: Paving and line painting are complete, signage to be completed this week.
September 22, 2025: Pavement spot repairs, asphalt milling and small crack repairs complete. Asphalt paving underway, which will be followed by line painting.
September 15, 2025: Pavement spot repairs nearing completion with asphalt surface milling complete. Small crack milling and repair ongoing, which will be followed by asphalt paving.
September 4, 2025: Pavement rehabilitation is underway with selective spot repairs ongoing, which will be followed by milling of the existing asphalt surface.
August 2025: Construction contract has been awarded. Construction anticipated to start August 25th.
July 2025: Design is complete, construction request for quotation has been posted. Construction anticipated to be started in July/August 2025.
April 2025: No updates.
March 2025: No updates.
February 2025: Design is underway, construction is anticipated to be started in July of 2025.