Sundance Road, West of TransAlta Plant
Project Description:
Design and rehabilitation of Sundance Road West of TransAlta Sundance Plant.
Scope of Work:
The project includes design and construction which is focused on improving road condition and rideability.
Schedule:
Est. Start date: Preliminary design started April 2025. Construction expected late summer of 2026.
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): Knelsen Sand & Gravel Ltd, Jasmine Young, 780-228-6361, jasminey@knelsen.com
Consultant (Secondary Contact): Stantec, Glen Rau, 780-813-0749, glen.rau@stantec.com
Parkland Project Engineer: Jeremy Hemsing, P.Eng. 780-919-0652, jeremy.hemsing@parklandcounty.com
Updates:
July 22, 2026: Construction notice posted under the document section. Scheduled to start construction August 6th, with potential slight traffic delays.
July 7, 2026: Construction start up delayed due to recent rains. Tentative construction start up is the middle of August.
June 2, 2026: Construction tentatively scheduled to begin by the end of June.
May 1, 2026: Construction Contract Awarded. Tentative Construction start Summer 2026.
April 7, 2026: Award for the construction contract is ongoing. Construction is anticipated to occur in the summer of 2026.
February 27, 2026: Procurement of a construction contractor is ongoing. Construction anticipated to occur in summer of 2026.
January 30, 2026: Engineering design complete. Procurement of a construction contractor is ongoing.
September 15, 2025: No Update
July 4, 2025: No Update
June 3, 2025: No Update.
April 28, 2025: Engineering consultant procured. Geotechnical investigation and preliminary engineering ongoing.
Location: