Surfaced Road Rehabilitation Project - Twp 512, RR 275 to RR 280

Share Surfaced Road Rehabilitation Project - Twp 512, RR 275 to RR 280 on Facebook Share Surfaced Road Rehabilitation Project - Twp 512, RR 275 to RR 280 on Twitter Share Surfaced Road Rehabilitation Project - Twp 512, RR 275 to RR 280 on Linkedin Email Surfaced Road Rehabilitation Project - Twp 512, RR 275 to RR 280 link

Project Description:

Road rehabilitation at Twp 512 (Holborn Rd) from RR 275 to RR 280.


Scope of Work:

The project includes reshaping and recompacting the existing road materials followed by placement of new asphalt.


Schedule:

Est. Start date: June 24, 2024 – September 2024

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Contractor (Primary Contact): Park Paving NA

Consultant: (Secondary Contact): WSP / NA

Parkland Project Officer: Trevor Lucas, 780-217-4629, trevor.lucas@parklandcounty.com


Updates:

September 25, 2024: The 2024 Surfaced Road Reconstruction Program has been completed and is in the one year warranty period.

June 2024: Park Paving is starting the work on June 24, 2024. See the attached construction notice from Park Paving.

May 2024: Parkland is currently in the process of procuring a contractor to complete the work.


Location:

Project Description:

Road rehabilitation at Twp 512 (Holborn Rd) from RR 275 to RR 280.


Scope of Work:

The project includes reshaping and recompacting the existing road materials followed by placement of new asphalt.


Schedule:

Est. Start date: June 24, 2024 – September 2024

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Contractor (Primary Contact): Park Paving NA

Consultant: (Secondary Contact): WSP / NA

Parkland Project Officer: Trevor Lucas, 780-217-4629, trevor.lucas@parklandcounty.com


Updates:

September 25, 2024: The 2024 Surfaced Road Reconstruction Program has been completed and is in the one year warranty period.

June 2024: Park Paving is starting the work on June 24, 2024. See the attached construction notice from Park Paving.

May 2024: Parkland is currently in the process of procuring a contractor to complete the work.


Location:

Page last updated: 25 Sep 2024, 03:37 PM