Wabamun Lagoon Rehabilitation
Project Description:
Berm repairs and replacement of manholes and valves at the Wabamun Lagoon
Scope of Work:
Replacement of lagoon inlet manhole, control structure between facultative cell and storage cell A, and replacement of valves at Wabamun Lagoon. Berm repair was completed in 2024, only clean-up work remaining.
Schedule:
Est. Start date: May 21, 2025 – July 1, 2025
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): Jason Stiksma, CKB Construction, Jstiksma@ckbconstruction.com
Consultant (Secondary Contact): Greg Germain, ISL Engineering, ggermain@islengineering.com
Parkland Project Officer: Ryan McCaffrey, 780-217-9196, ryan.mccaffrey@parklandcounty.com
Updates:
October 1, 2025 – Project Complete. All deficiencies addressed and work will be monitored throughout the remainder of the warranty period.
June 18, 2025 – All construction and final walkthrough completed. Warranty now in effect until June 18, 2027.
June 4, 2025 – New Inlet structure installed and prepped for backfill. Control structure MH-097 removal completed, new control structure installed. Awaiting concrete for benching and thrust blocks prior to backfill.
May 28, 2025 – Inlet structure has been removed, forcemain bypass to anaerobic cell installed. Rebar layout installed and prepped for concrete pour of new inlet base slab.
Location:
Wabamun Lagoon