Stormwater Rehabilitation Program - Big Lake

Share Stormwater Rehabilitation Program - Big Lake on Facebook Share Stormwater Rehabilitation Program - Big Lake on Twitter Share Stormwater Rehabilitation Program - Big Lake on Linkedin Email Stormwater Rehabilitation Program - Big Lake link

Project Description:

Repair several cracked storm mains in and around Country Squire Estates using trenchless lining techniques to prevent more disruptive and costly repairs in the future.


Scope of Work:

Trenchless Repair using Cured in Place Pipe (CIPP) of six storm mains.


Schedule:

Est. Start date: July 2025 – November 2026

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Contractor (Primary Contact): TBD in 2026

Consultant: (Secondary Contact): AECOM Canada, Jody Cherdarchuk, Jody.Cherdarchuk@aecom.com

Parkland Project Officer: Brandi Dechkoff, 780-968-8888 ext 780-800-9304, brandi.dechkoff@parklandcounty.com


Location:

Four storm main in and adjacent to Country Squire Estates.

Updates:

April-May 2026: Contractor Pre-qualification Initiated & Affected Resident Outreach

Winter 2025/2026: Design Review and finalize scope of work

July – September 2025: Initial Design

2026: Construction which should be approximately 1 week

Project Description:

Repair several cracked storm mains in and around Country Squire Estates using trenchless lining techniques to prevent more disruptive and costly repairs in the future.


Scope of Work:

Trenchless Repair using Cured in Place Pipe (CIPP) of six storm mains.


Schedule:

Est. Start date: July 2025 – November 2026

Schedule can change without notice, follow page for monthly updates.


Project Co-ordinator:

Contractor (Primary Contact): TBD in 2026

Consultant: (Secondary Contact): AECOM Canada, Jody Cherdarchuk, Jody.Cherdarchuk@aecom.com

Parkland Project Officer: Brandi Dechkoff, 780-968-8888 ext 780-800-9304, brandi.dechkoff@parklandcounty.com


Location:

Four storm main in and adjacent to Country Squire Estates.

Updates:

April-May 2026: Contractor Pre-qualification Initiated & Affected Resident Outreach

Winter 2025/2026: Design Review and finalize scope of work

July – September 2025: Initial Design

2026: Construction which should be approximately 1 week

Page last updated: 07 Apr 2026, 11:44 AM