Project Description:
Repair several cracked storm mains in and around Country Squire Estates using trenchless lining techniques to prevent more disruptive and costly repairs in the future.
Scope of Work:
Trenchless Repair using Cured in Place Pipe (CIPP) of four storm mains.
Schedule:
Est. Start date: July 2025 – September 2026
Schedule can change without notice, follow page for monthly updates.
Four storm main in and adjacent to Country Squire Estates.
Updates:
July – September 2025: Initial Design and Adjacent Property Outreach
2026: Construction which should be approximately 1 week
Project Description:
Repair several cracked storm mains in and around Country Squire Estates using trenchless lining techniques to prevent more disruptive and costly repairs in the future.
Scope of Work:
Trenchless Repair using Cured in Place Pipe (CIPP) of four storm mains.
Schedule:
Est. Start date: July 2025 – September 2026
Schedule can change without notice, follow page for monthly updates.