Bridge Replacement – Twp 510 East of RR50 File 70230
Project Description:
Replacement of Bridge File 70230 on Twp Rd 510 East RR 50
Scope of Work:
Removal of existing bridge culvert and installation of 5230mm bridge culvert.
Not included in scope of work – upgrading of Twp Rd 510.
Schedule:
Est. Start Date: June 2025
Est. Completion Date: October 2025
Schedule can change without notice, follow page for monthly updates.
Project Co-ordinator:
Contractor (Primary Contact): Craig Barsi, (780) 786-4014, barsient@telus.net
Consultant: (Secondary Contact): Kirk Morris, P.Eng. (780) 416-3030, ParklandCountyMPA@mpaeng.ca
Parkland Project Manager: Franco Giammarioli, E.I.T. (780) 968-8888 ext. 8390 franco.giammarioli@parklandcounty.com
Updates:
October 3, 2025 – Construction is nearing completion, and the entire culvert has been installed. Contractor is working on installing riprap and completing road construction to final grade.
July 25, 2025 – Barsi will mobilize to site to begin construction. A staged detour with single lane closures and temporary traffic lights will be in place for the duration of the project. Road will remain open during construction.
June 2, 2025 – Pre-construction signage is installed. Construction expected to begin in June 2025 and traffic accommodation information will be posted once it is available.
May 5, 2025 – Construction expected to begin in June 2025.
February 2025 – Construction contract awarded. Anticipated construction start is the summer of 2025.
January 2025 – No Update
December 2024 – Design is approved, construction will be started following contract award, anticipated to be summer (June/July 2025). Township 510 will remain open to traffic during construction. Expect delays while traveling along Twp 510.
Location:




