Wabamun Cured In Place Pipe
Project Description:
As part of an overall wastewater rehabilitation program in Wabamun, a Cured in Place Pipe (CIPP) Contractor will be hired to install liners within the Hamlet.
Cured-in-Place-Pipe Lining (CIPP) is a trenchless method of sewer rehabilitation. It requires little or no digging and significantly less time to complete than other sewer repair methods. It is suitable for repairing both short and long runs of pipes that do not need to be upsized.
Scope of Work:
Approximately four (4) kilometers of wastewater mains will be rehabilitated using CIPP technologies. The scope of work includes pre-inspection and pipe preparation, liner design and supply, installation of liners, temporary flow control, reinstatement of service laterals, post lining and warranty camera inspections.
Schedule:
Est: June 2024 – November 2024
Project Co-Ordinator:
Contractor (Primary Contact):
Insituform Technologies Ltd – Christian Taylor, 780-217-1986, ctaylor@azuria.com
Consultant (Secondary Contact): ISL Engineering
Parkland Project Officer: Ryan McCaffrey, 780-968-8888 Ext. 8606, ryan.mccaffrey@parklandcounty.com
Updates:
November 1, 2024: The lining phase of work was completed on October 23. Insituform will be completing final CCTV inspections of the sanitary pipes over the next 1-2 weeks and should be fully demobilized by the end of November.
October 1, 2024: Work for the lining phase began on September 16, 2024. This phase is expected to take approximately 3-4 weeks to complete. Following the lining phase, the Contractor will be completing post lining inspections and will likely be in Wabamun until mid-late November.
September 1, 2024: Insituform is slightly delayed in mobilizing to being the lining phase of work. They are planning to mobilize in mid-September and will be accelerating their schedule to minimize delays.
August 1, 2024: Regional water restrictions pushed the schedule back about 1 week, Insituform is remobilizing on August 7 to resume flushing and CCTV within Wabamun. Remaining work for this phase is expected to take approximately 2 weeks.
July 1, 2024: Insituform is scheduled to mobilize and begin pre-cleaning and inspection of the sanitary sewer mains on July 11, 2024. This phase of the work is expected to take approximately 1 month to complete. The liner installation phase is scheduled to begin in mid-September.
June 1, 2024: Work is anticipated to begin in mid-June and is expected to take approximately two months. The first phase is pipe cleaning and preparation (~1 month) and the second phase is liner installation (~1 month).
May 1, 2024: Contract awarded to Insituform Technologies Limited
April 1, 2024: Pending contract award
March 2024: Construction quotes close March 27, 2024.
Location: